項(xiàng)目進(jìn)度 Project schedule均化庫安裝至第十節(jié)板,水泥庫庫頂梁、加勁梁預(yù)制完成100%,減壓錐完成95%。 The homogenization silo is installed to the tenth section of the slab, the prefabrication of the cement silo roof beam and stiffening beam is 100% completed, and the decompression cone is 95% completed. |